There are many ways to start a new budget cycle. To see them all, click here. This article walks through the specific steps to create a budget for the next fiscal year based on the current year and the previous year's actuals. For example, assuming a calendar fiscal year start, if it is currently September and you have closed August, this method will use January - August actuals of the current year and September - December actuals of the prior year.
Step by Step:
- Go to Planner > Planner Setup.
- If needed, navigate to the current fiscal year.
- Click Create Budget.
- Choose Based on Prior Year's Actuals and Budget. (NOTE: This will load all of the prior year actuals.)
- Choose any budget to copy.
- Give the new budget a title such as "Last Year's Actuals".
- Click Create Budget.
- Go to Dashboard > Updater and wait for the task to complete.
- Go to Planner > Planner Setup.
- If needed, navigate to the next fiscal year.
- Click Create Budget.
- Choose Based on Prior Year's Actuals and Budget. (NOTE: This will load all of the prior year actuals, but won't touch the prior-prior year actuals in later months, loaded in step 4.)
- Choose the budget created in the steps above.
- Give the new budget a title such as "Working Budget".
- Click Create Budget.
- Go to Dashboard > Updater and wait for the task to complete.
- Go to Planner > Planner Setup.
- Select the budget just created.
- Click Set as Planner.
Was this article helpful?